Technical Infrastructure and Hyperscale Data Centers
Groundwork
Completed

Hamang Transformer Station

The new substation replaces the facility from the 1950s and has been built to ensure a stable power supply for Oslo, Bærum and the wider Viken region. The station is located directly above the Bjørnegård Tunnel on the E16, which has made the project technically demanding and placed strict requirements on foundation works, mass handling, and coordination.

Technical Infrastructure and Hyperscale Data Centers
Groundwork

Client

Statnett

Construction period

April 2021

-

March 2024

Contract value

40 MNOK

Enterprise format

Totalentreprise 8407

Geography

Sandvika, Bærum kommune

About the Project

The project involved extensive groundwork associated with the construction of a new, compact, gas‑insulated transformer station. The site lies primarily on bedrock, which was excavated by hydraulic breaking. An extensive pile foundation , more than 100 piles, was installed to ensure proper load transfer and long‑term stability.


The transformer section of the station stands on existing concrete piles located very close to the Bjørnegård Tunnel, requiring precise coordination of both earthworks and structural construction.

In addition, MD’s groundwork formed part of the establishment of a concrete beam‑grid structure, which acts as a load‑bearing system between the station and the tunnel infrastructure below. The work was carried out within a very confined area, requiring continuous coordination with the Norwegian Public Roads Administration (Statens vegvesen), which completed its E16 works immediately prior to the project start.

The building structure is constructed in concrete and partially clad with Cembrit panels, with insulation standards adapted to the different functional zones of the facility. The new station is divided between Statnett (420 kV) and Elvia (132 kV and 47 kV), mirroring the configuration of the electrical installations.

Work performed by MD

  • Establishment of the excavation pit and terrain adjustments
  • Rock breaking and handling of materials with varying quality
  • Handling, temporary storage and reinstatement of masses
  • Excavation and groundwork in areas with dense underground infrastructure Installation of extensive infrastructure for roads, underground cable routes and water/wastewater systems
  • Foundation‑preparation works, including pile locations
  • Contribution to the construction of the concrete beam‑grid forming the station’s foundation structure
  • Preparation of site facilities and access routes in a highly confined work area
  • Coordination with other stakeholders to ensure safe progress in challenging surroundings

Design and Complexity

The facility is situated in a highly constrained area surrounded by extensive infrastructure — roads and tunnels, a vulnerable salmon river, and protected buildings — leaving very limited space for site setup, storage and equipment movements. This placed strict requirements on detailed HSE planning, progress planning, and continuous coordination across all disciplines.

Variable Ground Conditions
Simultaneous Works Involving Critical Infrastructure
Delivery of Large Transformers